You are in the planning process of a $1b project. You realize that your schedule requires more resources in certain months of the project than that are available to you. Your senior management has clearly instructed that you will not be able to obtain any additional resources for the project. So, you instruct your planner to adjust the schedule to accommodate these constraints. What are you instructing the planner to do?

1.Crashing
2.Resource leveling
3.Programme Evaluation and Review Technique
4.Fast tracking

Please provide your answer with justification. Justifying your answer with explanation helps you to remember the concept and also help others to understand. Thanks.

Regards,
Manick
PMP Lessons Learned
avatar
Admin
Admin

Posts : 11
Join date : 2017-04-14

http://pmpexamgroup.forumotion.com

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum